Events

Events

Yuri Romanchenko Ice Strengthened Buoy Boat of 02780M Project (Construction Number 51) Accepted

On September 15, 2016 the Acceptance Committee, appointed by FSUE “Rosmorport” General Director A. V. Tarasenko Order No. 389 dated 17.08.2016 accepted Yuri Romanchenko ice strengthened buoy boat of 02780M Project (Construction Number 51).

Construction, testing and commissioning of the project 02780M Yuri Romanchenko boat was carried out under technical supervision of inspectors of the Petrozavodsk Site Inspection of the Russian Maritime Register of Shipping of the Baltic Basin.

It is the second boat constructed under the 02780M project at the Onezhsky Ship Building and Ship Repairing Plant, under FSUE “Rosmorport” order.

For reference:

Yuri Romanchenko ice strengthened buoy boat was launched on June 10, 2016 and is intended for aids to navigation (AI) maintenance, ensuring safety of navigation in the country's seaport water areas.

Main specifications:

Vessel class

 KM  Iсe3 R3-RSN AUT3

Overall hull length, m   

22,697

Overall hull breadth, m

7,026

Draught overall, m

1,67

Operating speed, knots

7-9

Crew / Special personnel, people

2/5