List of Vessels Being Constructed for FSUE “Rosmorport”
The vessel is designed to ensure year-round operation of the freezing seaports in the Far Eastern basin
Type of vessel: |
КМ Icebreaker7 ![]() |
Length: | 119.8 m |
Width: | 27.5 m |
Draft: | 8.5 m |
Speed: | 17 knots |
Icebreaking capability: | up to 2 m |
Fuel reserve autonomy: | 29 days |
Crew: | 35 people |
OJSC "Leningrad Shipyard "Pella"
State contract No. 506/OPED-19 of September 25, 2019
September 30, 2024
The vessel is designed for operation in the water areas of the North-Western basin seaports
Type of vessel: |
КМ Icebreaker7 ![]() |
Length: | 119.8 m |
Width: | 27.5 m |
Draft: | 8.5 m |
Speed: | 17 knots |
Icebreaking capability: | 1.5 m |
Fuel reserve autonomy: | 40 days |
Crew: | 35 people |
Special personnel | 22 people |
Vyborg Shipyard PJSC
Vessel project design documentation developed by: PKB Petrobalt LLC
Vessel project design documentation developed by: PKB Petrobalt LLC
State contract No. 273/OPED-21 of November 25, 2021
In November 2021, a state contract for the construction of the vessel was signed.
On November 16, 2022, the keel was laid.
The vessel is planned to be handed over to the enterprise on December 10, 2024.
On November 16, 2022, the keel was laid.
The vessel is planned to be handed over to the enterprise on December 10, 2024.